Buckingham Group owed £108m at collapse


Buckingham Group imploded owing greater than £108m, in line with its directors.

The tier one contractor collapsed earlier this month after struggling “vital and rising losses incurred on key sports activities and leisure contracts resulting from inflation pressures”, in line with an announcement of proposals doc written by directors from Grant Thornton.

Buckingham, which had 669 workers and workplaces in Stowe, Birmingham, Doncaster, London and Manchester, additionally sustained “losses […] on a key civils/construct mission, delays on contracts and delays on recovering vital works in progress balances”, the doc states.

Grant Thornton stated the problems created a cashflow disaster, as receipts had been acquired on the finish of the month whereas giant subcontractor funds had been due mid-month.

The group owes £108m, with 1,258 claims having been lodged with the administrator. Though most of those claims relate to separate companies, some suppliers have lodged a number of claims.

Grant Thornton stated it anticipated abnormal preferential collectors to be paid in full, with cost additionally set to be made to secondary preferential collectors. Nonetheless, it stated “it’s unclear whether or not there can be a return to the unsecured collectors”, including that it trusted “sure claims and debtor realisations”.

Buckingham had £4.8m in a checking account with HSBC – one among its collectors – when it went below, though this cash has but to be transferred to the administrator’s account.

The administrator stated: “Because of the rising losses being incurred on contracts and a scarcity of visibility on key cashflow issues akin to HM Income & Customs (HMRC) Time to Pay [arrangements] (TTP) and contract adjudications, the advance price on funding being offered by the corporate’s bill finance facility was diminished to nil in July 2023.

“This, along with HMRC rejecting a proposal for an additional TTP in August 2023 and rising creditor stress resulting from not having the ability to meet the complete provider/subcontractor cost run, resulted in Grant Thornton being engaged by the corporate on 16 August 2023 to discover a sale of enterprise and belongings.”

Grant Thornton was unable to promote the enterprise, though it bought the corporate’s rail division and associated belongings to Kier for £9.6m. The guide worth of the belongings bought to Kier was roughly £11m, it stated.

Kier paid £5.67m to take over Buckingham’s dwell rail tasks, £1.89m for its HS2 contract and round £333,000 every for retentions, money owed and work in progress.

Kier paid an additional £1 every for buyer contracts; a West Midlands buyer contract; provider contracts; enterprise mental property; goodwill; enterprise information; info know-how; inventory; and plant and gear.

Grant Thornton stated earlier than Buckingham collapsed it approached “numerous debt suppliers, along with a variety of particular scenario funds, personal buyers and UK and oversees commerce consumers”.

Nevertheless it added: “Regardless of contacting in extra of 20 events, no social gathering was prepared to supply extra debt finance to the corporate or was eager to pursue a solvent buy of the corporate’s share capital.”