First pier full for Water Orton viaducts

First pier full for Water Orton viaducts

[ad_1]

The first pier is cast
The primary pier is forged

The 2 Water Orton viaducts kind a part of Delta Junction, HS2’s most advanced community of constructions within the West Midlands, and at 20-metres excessive are among the many tallest constructions on the road.

HS2’s fundamental works contractor for the West Midlands, Balfour Beatty Vinci (BBV) is constructing the 1,400-metre lengthy north-south constructions to attach HS2’s Birmingham Curzon Avenue Station with Crewe and Manchester.

Delta Junction is a triangular part of the high-speed railway made up of 9 precast segmental viaducts, embankments, and different bridging constructions, with round 10km of observe crossing a community of motorways, roads and rivers.

The Water Orton viaducts – east of the M42 and Lichfield Street – will carry 700 metres of HS2 observe over the River Tame and a community of present transport hyperlinks, together with the Birmingham-Peterborough line, working between Water Orton and Coleshill Parkway stations.

Completion of the primary pier represents an indication of progress for BBV.

Whereas elsewhere on HS2 a lot use is being fabricated from precast concrete segments, these piers are forged in situ with bespoke formwork. The reinforcement cage is assembled in a rebar manufacturing facility close to Coleshill.

The deck segments will likely be precast, nevertheless, produced at HS2’s close by purpose-built Kingsbury manufacturing facility close to Lea Marston. The outside manufacturing facility is making 2,742 segments for your complete Delta Junction – greater than 6km of post-tensioned viaduct. The segments will likely be trucked to web site on devoted haul roads.

Related Information

Sam Hinkley, HS2 senior undertaking supervisor for Delta Junction, mentioned: “That is one other key second for HS2 within the West Midlands as work ramps up on some of the advanced sections of the entire route. The Delta Junction is HS2’s key interchange the place the brand new zero-carbon excessive pace railway will join between London, the midlands and the north.

“Minimising disruption to native communities on this space has been a key consideration in our planning, together with using revolutionary pre-cast building methods, and haul roads to take lorries off native roads.”

As soon as the piers are constructed, the spans will likely be constructed by elevating every phase from a brief suspension tower erected on prime of every pier. When every span is full, the suspension tower will likely be disassembled and moved alongside the viaduct to construct the following span.

An ‘match-casting’ method sees every viaduct phase forged in opposition to its neighbouring phase in a manufacturing line. Every phase is exclusive, and adjustable by as little as 5mm. Pouring every phase in opposition to the earlier one ensures the entire arch suits collectively when assembled on web site.

Artist's impression of the Water Orton Viaducts
Artist’s impression of the Water Orton Viaducts

BBV building director David Waite mentioned: “Witnessing the elimination of the shuttering to disclose the primary accomplished pier for Water Orton viaduct was an necessary event for the 1,100 individuals who make up the Delta workforce.

“With the manufacturing line on the Kingsbury pre-cast manufacturing facility now in full swing, we are going to begin to see the viaduct take form over the approaching months, with the primary span as a result of be accomplished early subsequent 12 months.”